15.09 Unpacking the new MTV-7 C/183-51
prop.
Note; building progress will continue from medium October after
few months silence here.
31.05 Makes ready for priming wing
parts, so can be closing the wings.
10.05
Work on left aileron/wing hinges etc
12.04 cutting and adjusting the canopy
glass
08.02
Finish the bracket for gas-struts, and do the last tilt-up
frame rivet and assembly. Priming the canopy tilt-up frame,
instrument panel skin, and the roll bar
24.01.09
Working on the brackets and base for the roll bar.
18.01.09 aiii...Long winter pause in the
building, but has now again begin to work on airplane project.
Hopefully I will be able to attend 5 to 15 hour each weekend
from now on.
16.11
Working on the roll bar.
25.10 Working on instrument panel
wiring, and added a 2 1/4" airspeed and altitude instrument.
28.09 Drill and tap connection rod for
canopy opening latch
19.08
Priming
outside body.
16.08
Priming vertical
stab., rudder, and parts for horizontal stab., also
spinner and seat back plates. To morrow will prime the all aircraft body!
21.06 Mounting spinner back plate to propeller
hub.
25.05 Install fuel sensor in fuel tank.
!8.05 Finished inside cabin fuel line and fuel
thank selector mount.
03.05
Finish air
filter lock mod. Make cover for fuel pumps (center consol)
27.04
assembling the
electric aileron trim
(picture of
finish mounted trim servo.)
22.04
Mounting
the engine ECU, and temporary fit air box to engine
installation.
14.04
Continue on the quick release system, finish
rudder pedals.
07.04
Mounting the coolant expansions thank to firewall
03.04
Make center consol
30.03 Make fuel lines from firewall and
backwards
29.03 Gascolater, forward firewall fuel line in place.__________________________
|